19-07-08
2008.07.19
- Core is now progressing up to Level 13.
- Level 10 First Pour is being formed.
- Screens yet to complety be jumped above Level 6
- Ducting was loaded into Level 5 today.
- Level 4 curtain wall starter panels are progressing on the South Elevation
- Welding of curtain wall brackets to Level 5 has started
- Crane #1 on George Street is to Jump early next week.