02-02-09
So it has taken a while for everyone to warm back up. The end of the project is now visible and people can see the end.
Currently the slabs to level 28 are being poured, Curtain wall is being installed on Level 19 & the plant to Level 14 is being installed. The balance of the cladding on this floor will be finished within the next couple of weeks. The contrast of the anodised louvres and zinc cladding to the main walls is pretty impressive.
Work on the podium floors has kicked off with avengence with a reasonable amount of steelwork, cladding and glazing started. Internal finishes to the low rise floors are going well.