Well it has been raining all day today – breaks up the monotony of the continual dry weeks. Work is going crazy; the core (where the lifts are contained) is up to Level 32, the slabs to Level 30 and Curtain Wall Level 21.

The podium is now a hive of activity, with Cladding and glazing occuring everywhere. The Plantroom walls on Level 14 are almost complete and the space is slowly getting filled up with plant.